Debriefs and challenges
Navigating the tender debrief
The award letter is the most information a buyer will ever give you about how your bid was read. Most bidders file it and move on. Here is how to use it, and the clock that starts the day it arrives.
Losing a tender stings. The natural response is to file the award letter, mutter about the winner’s price and move on to the next bid.
That wastes the most valuable feedback you will get all year. The award letter, and the debrief that can follow it, is the only time a buyer tells you in writing how an evaluation panel actually read your work. Used well, it changes the next bid. Occasionally, it changes this one.
Start with the letter, and the clock
For contracts above the EU thresholds in Ireland, the buyer must notify unsuccessful tenderers of its award decision before the contract is signed. That notice must set out the characteristics and relative advantages of the tender selected and the name of the successful tenderer. It also opens a standstill period, during which the contract cannot be concluded. The standstill is at least 14 calendar days where the notice is sent electronically, and 16 days where it is sent by other means.
In the UK, the Procurement Act 2023 (in force since 24 February 2025) works differently. Each supplier that submitted an assessed tender gets an assessment summary. The standstill then starts when the buyer publishes its contract award notice, and runs for at least eight working days from that day.
Either way, the period is short. If anything in the letter troubles you, the time to act is the day it arrives, not after the next team meeting.
This is general information, not legal advice. The rules have exceptions, and time limits for a challenge are strict. If you are considering one, speak to a solicitor immediately.
Read the letter the way the panel wrote it
Before asking for anything else, take the letter apart:
- Your scores against the winner’s, criterion by criterion. Where is the gap? Is it spread evenly, or concentrated in one or two criteria?
- The weightings. A 3-mark gap on a 40% criterion matters more than a 6-mark gap on a 10% one.
- The reasons given. Look for the words the panel actually used. “Did not demonstrate” usually means missing evidence. “Generic” usually means you answered the question without answering it for this buyer.
- The winner’s advantages. The relative advantages of the winning tender often describe, almost exactly, what your response lacked.
- Price versus quality. Did you lose on quality, on price or on both? It decides what you change next time.
Most of the learning is in this step, and it costs nothing.
Decide what you want before you ask for more
Before requesting a debrief meeting, be clear about your goal. There are three honest answers, and they lead to different conversations:
- To improve. You want to understand the gap so the next bid scores higher. This is the usual case, and the most valuable.
- To understand a result that doesn’t add up. The scores, the reasons and your own reading of your bid don’t reconcile, and you want to know why.
- To keep a challenge open. Something in the process looks wrong, and you need facts quickly while the standstill period runs.
Buyers rarely concede errors and reverse decisions, though competitions are sometimes cancelled and re-run. A formal challenge is expensive and slow, and the burden of proving that something went wrong sits with the challenger. That is a reason to be clear-headed, not a reason never to ask.
Questions worth asking
Keep questions about your tender and the published process. Buyers cannot share other bidders’ confidential information, and a debrief is not a renegotiation. Within those limits, good questions include:
On your submission
- Which parts of our response scored well, and which cost us most?
- Were any parts unclear, or read differently from what we intended?
- Where did the panel look for evidence and not find it?
On the evaluation
- How was each criterion applied to our response, against the published scoring scheme?
- In the criteria where the gap was largest, what did the stronger responses do that ours did not?
- Was the evaluation moderated, and did our scores change at moderation?
On the competition
- How many tenders were received and assessed?
- Where did we rank, overall and on quality?
For next time
- Are there upcoming requirements where our approach might be a better fit?
- Is there anything in how we engage before or during a tender that you would like us to do differently?
Ask, too, that anything new you are told is consistent with the reasons already given in writing. Reasons offered for the first time at a debrief carry less weight than those in the letter, and a mismatch is worth noting.
Run the meeting well
- Send questions in advance, so the buyer can bring the right people and real answers.
- Bring the people who wrote the bid, not only the sales lead. They will hear what the panel meant.
- Take a careful note, and send it back afterwards as a summary of what was said.
- Listen more than you argue. You are there to learn how you were read, not to re-make the case.
Will it damage the relationship?
It’s a common worry, and usually unfounded. Buyers are professionals; requesting reasons is routine and expected. Approached calmly and constructively, a debrief often improves the relationship: it shows you take the buyer’s requirements seriously and want to meet them better.
What does damage relationships is a debrief used as an ambush, or a challenge threatened without substance. Keep those separate. If a challenge is genuinely in prospect, take legal advice and let that advice shape what you ask.
Make it count next time
The best debrief ends in a short written note to your bid library:
- the two or three criteria where the gap was largest;
- what the winning response appears to have done differently;
- the evidence you lacked, and where you will find it next time;
- one change to your bid process.
Then check whether your next bid actually applied it. That is how a lost tender pays for itself.